Sika® Bonding Primer
Sika® Bonding Primer is a two-component, water-based epoxy primer to consolidate substrates and enhance the adhesion of SikaRoof MTC®, Sikalastic®, Sikafloor® and Sikagard® products
- Fast curing - overcoat possible after 1 - 2 hours
- Long pot life - up to 12 hours
- Low odour - water-based product
- Consolidates dusty or friable surfaces
- Uniforms the absorbency of the substrate
- Enhances adhesion to a broad range of substrates
- Easy application by brush or roller
Usage
Versatile primer for use with:- SikaRoof® MTC
- Sikalastic® roofing systems
- Sikafloor® balcony waterproofing systems
- Sikagard® hygiene coatings
- Suitable for use on concrete, masonry, tiles, insulation foams, bituminous surfaces, plaster, cementitious renders, screeds and mortars.
Advantages
- Fast curing - overcoat possible after 1 - 2 hours
- Long pot life - up to 12 hours
- Low odour - water-based product
- Consolidates dusty or friable surfaces
- Uniforms the absorbency of the substrate
- Enhances adhesion to a broad range of substrates
- Easy application by brush or roller
Packaging
15.0 l (~15.546 kg) unit | 12 l component A 3 l component B |
Colour
Milky green liquid resin
Product Details
Chemical Base
Epoxy, waterborne and polyamine curative
Shelf Life
24 months from date of production
Storage Conditions
The product must be stored properly in original, unopened and undamaged sealed packaging in dry conditions at temperatures between +5 °C and +25 °C.
Higher storage temperatures may reduce shelf life of product.
Reference shall also be made to the storage recommendations within the safety data sheet.
Density
~1.03 kg/l (23 °C) | (EN ISO 2811-1) |
Application
Mixing Ratio
Component A : Component B = 4:1 (by volume)
Ambient Air Temperature
+5 °C min. / +40 °C max.
Relative Air Humidity
80 % r.h. max.
Dew Point
Beware of condensation.
The substrate and uncured coating must be ≥3 °C above dew point.
Substrate Temperature
+5 °C min. / +40 °C max.
Substrate Moisture Content
Visible damp free (maximum 18 % wood moisture equivalent).
≤6 % pbw moisture content Test method: Sika®-Tramex meter
≤4 % CM - measurement or Oven-dry-method.
No rising moisture according to ASTM (Polyethylene-sheet).
Waiting Time / Overcoating
Before applying any recommended SikaRoof® MTC, Sikalastic® and Sikafloor® products on Sika® Bonding Primer, allow:
Substrate temperature | Minimum waiting time | Maximum waiting time |
+10 °C | 4 hours approx. | 7 days |
+20 °C | 2.5–3.5 hours approx. | 7 days |
+30 °C | 1 hour approx. | 7 days |
Before applying Sikagard® products on Sika® Bonding Primer allow:
Substrate temperature | Minimum waiting time | Maximum waiting time |
+10 °C | 24 hours approx. | 7 days |
+20 °C | 8 hours approx. | 7 days |
+30 °C | 6 hours approx. | 7 days |
Times are approximate and will be affected by changing ambient conditions particularly temperature and relative humidity.
Consumption
Apply in one to two coats, with a consumption of 0.10 kg/m2 approx. per coat depending upon surface roughness and absorption.
Note: For metal substrates apply 1x Sikalastic® Metal Primer (0.20 kg/m2 approx.) instead of Sika® Bonding Primer (please refer to Sikalastic® Metal Primer Product Data Sheet for further information).
These figures are theoretical and do not include for any additional material required due to surface porosity, surface profile, variations in level and wastage.
SUBSTRATE QUALITY
The surface must be sound, of sufficient strength, clean, dry and free of dirt, oil, grease and other contamination. The concrete substrate must be sound and of sufficient compressive strength (minimum 25 N/mm2) with a minimum pull off strength of 1.5 N/mm2.
SUBSTRATE PREPARATION
All surfaces to be coated should be thoroughly cleaned by conventional means.
Inspect the substrate.
Spalling, flaking or damaged areas should be repaired using compatible materials to match surroundings or replaced as necessary.
If in doubt apply a test area first.
Tiles have to be prepared mechanically - glazing has to be removed.
Grinding may be necessary to level the surface.
For detailed information regarding substrate quality / preparation and primer chart please refer to Method Statement.
APPLICATION
Prepare Sika® Bonding Primer by adding component B into component A container, mix with an electric drill until a homogeneous light green colour is achieved and the product is free of streaks. Sika® Bonding Primer can be applied by short-piled roller, brush or airless spray. Allow primer to dry sufficiently (see table waiting time / overcoating) before overcoating.
CLEANING OF TOOLS
Clean all tools and application equipment with water immediately after use. Hardened and/or cured material can only be removed mechanically.